D. R. Reynolds Company worked diligently with East Side Fire Department, when the NC DOT expanded the highway and they lost access to their building due to the wider road. During the pandemic, D. R. Reynolds Company was able to work through delays, shortages, embedded rock and meet the requirements of East Side Volunteer Fire Department on their timeline to get the project completed before the county road project took their space.

This project for East Side Fire consisted of a large meeting area, open concept kitchen, sleep quarters, over 7,000sf of truck bay storage and a full block and brick building.

  • Completed in 2020
  • 10,975 Total Square Feet
  • 7,013 Square Feet Bays
  • 3,960 Square Feet Office Space
  • 80’-0” Deep Bays